Date: prev next · Thread: first prev next last
2021 Archives by date, by thread · List index


On Mon, 14 Jun 2021 05:58:54 -0500
Wade Smart <wadesmart@gmail.com> wrote:

Question: does the meter per day have any relevance to the date?
Is a working day equal to a business day? -> Mon - Fri only?

Yes the meters per day mean what is the daily output. Different
services with different daily output. 

Service a need 10 meters par day.
Service b need 1 meters par day.
Service c need 3 meters par day.
Service d need 5 meters par day.

service a is finished in 25 days so start day is 07.03.2022 end 11.04.2022.
service d is finished in 50 days so start day is 07.03.2022 end 13.05.2022.

I had think with if:

=IF(A3="service a") ...

but more I not become idea and find not really something in net.

Yes only Mon to Fri.

Thank you
Silvio

-- 
To unsubscribe e-mail to: users+unsubscribe@global.libreoffice.org
Problems? https://www.libreoffice.org/get-help/mailing-lists/how-to-unsubscribe/
Posting guidelines + more: https://wiki.documentfoundation.org/Netiquette
List archive: https://listarchives.libreoffice.org/global/users/
Privacy Policy: https://www.documentfoundation.org/privacy

Context


Privacy Policy | Impressum (Legal Info) | Copyright information: Unless otherwise specified, all text and images on this website are licensed under the Creative Commons Attribution-Share Alike 3.0 License. This does not include the source code of LibreOffice, which is licensed under the Mozilla Public License (MPLv2). "LibreOffice" and "The Document Foundation" are registered trademarks of their corresponding registered owners or are in actual use as trademarks in one or more countries. Their respective logos and icons are also subject to international copyright laws. Use thereof is explained in our trademark policy.