Hi Eike,

I'd avoid changing existing Add-In functions, it's a source of hassle ;-) 

Fine, I prefer to keep away from the add-in code, too.

Rather implement an ODFF compliant NETWORKDAYS function at the interpreter [...]

OK, then there will be 3 NETWORKDAYS functions: Add-in, OOXML and ODFF:
Add-in is a subset of ODFF as Add-in misses the 4th argument (defining weekend days);
OOXML differs from ODFF as the 3rd and 4th argument are the other way round and the weekend day 
argument for OOXML uses a 7-character string of 0 and 1, whereas ODFF uses a list of numbers (0 and 
not 0).

The difference between OOXML and ODFF doesn't concern me, that I can solve easily in the code.
The difference between Add-in and ODFF looks problematic to me when using ODFF NETWORKDAYS with 2 
arguments and saving to xls.
And how about compatibility with documents saved before introduction of ODFF NETWORKDAYS? Are these 
regarded as Add-inn?

A solution (which I don't like) could be to assume that NETWORKDAYS with 2 or 3 arguments is 
Add-in, and with 4 arguments is ODFF. I don't know if this can be implemented.

I will start making the ODFF NETWORKDAYS function and rename the Add-in function to NETWORKDAYS_ADD.

Winfried

Context


Privacy Policy | Impressum (Legal Info) | Copyright information: Unless otherwise specified, all text and images on this website are licensed under the Creative Commons Attribution-Share Alike 3.0 License. This does not include the source code of LibreOffice, which is licensed under the Mozilla Public License (MPLv2). "LibreOffice" and "The Document Foundation" are registered trademarks of their corresponding registered owners or are in actual use as trademarks in one or more countries. Their respective logos and icons are also subject to international copyright laws. Use thereof is explained in our trademark policy.